OSA Tools Project Management · NIWC Pacific
IMS Status Date Oct 1, 2026 · Snapshot S-39 · Navique Corporation
Human-in-the-Loop

Approval Queue

Cera cannot execute controlled actions until an authorized human approves them.

APR-041

Proposed Schedule Update

AI DraftAwaiting Approval
Activity
Operational Assessment
Current Finish
Oct 28
Prepared by
Cera
Authority Level
L2 · Draft
Proposed Action
Update forecast narrative and create recovery-analysis task.
Reason
8-day baseline variance and critical-path proximity.
Evidence · 5 sources
Current IMSPrior IMS SnapshotActivity 4.3.1Baseline ScheduleStatus Update dated October 1
APR-042

Variance Narrative — M-013 Site Readiness

AI DraftAwaiting Approval
Activity
Site Readiness Certified
Current Finish
Oct 27
Prepared by
Cera
Authority Level
L2 · Draft
Proposed Action
Publish variance narrative to monthly program review package.
Reason
M-013 variance +7d exceeds 5-day reporting threshold.
Evidence · 3 sources
Current IMSExternal dependency registerVendor correspondence log
AI Draft · Human Approval Required
M-013 Site Readiness Certified is forecast for October 27, seven days beyond the October 20 baseline. The variance is driven by 5.1.4 Hardware Delivery Confirmation, where vendor ship-date confirmation through DLA remains outstanding. Remaining float on the path is two days. Recovery under evaluation: expedited shipment request (DEC-026) or resequencing rack preparation around partial delivery.
APR-043

Logic Correction — Restore 3.2.17 Successor

AI DraftAwaiting Approval
Activity
Integration Lab Decommission Plan
Current Finish
Oct 12
Prepared by
Cera
Authority Level
L3 · Execute With Approval
Proposed Action
Add FS relationship 3.2.17 → 3.2.18 in the working IMS copy for scheduler validation.
Reason
Open-ended activity detected (DCMA logic check).
Evidence · 3 sources
Current IMSPrior IMS Snapshot (logic diff)DCMA 14-Point check

Execution requires Level 3. Under the current Level 1 authority, approval records human intent; the Scheduler performs the change in the authoritative IMS.

APR-044

Weekly IMS Status Report Draft

AI DraftAwaiting Approval
Activity
Operational Assessment Complete
Current Finish
Oct 28
Prepared by
Cera
Authority Level
L2 · Draft
Proposed Action
Distribute weekly IMS status report to program stakeholders.
Reason
Weekly reporting cadence.
Evidence · 3 sources
Current IMSCera findings registerDecision register
APR-045

Status Request Tasks — 7 Stale Activities

AI DraftAwaiting Approval
Activity
External Interface Agreement Execution
Current Finish
Oct 13
Prepared by
Cera
Authority Level
L3 · Execute With Approval
Proposed Action
Create status-request tasks for owners of 7 stale activities in project tracker.
Reason
Status currency below threshold for 7 activities.
Evidence · 2 sources
Current IMS status datesStatus cadence plan

Execution requires Level 3. Under the current Level 1 authority, approval records human intent; the Scheduler performs the change in the authoritative IMS.