OSA Tools Project Management · NIWC Pacific
IMS Status Date Oct 1, 2026 · Snapshot S-39 · Navique Corporation
Thursday, October 1, 2026 · 07:00 status cycle

Good Morning, Project Manager

Cera has reviewed the latest Integrated Master Schedule and identified items requiring attention.

IMS Health Score
87 / 100
Stable

Cera Morning Assessment

Generated 07:00 · 11 sources · Confidence High · 93%
AI Observation

Since the previous IMS status period, I identified 37 schedule changes. Three milestones moved more than five working days, two activities entered the near-critical path, and 8 external dependencies remain unresolved.

4 items require Project Manager review.

No changes have been made to the authoritative IMS.

Cera Authority

L1 · Recommend

Cera may analyze and recommend actions but cannot modify the authoritative schedule.

Readiness for Level 2 · Draft72%
38/50
Validated recs
3.8%
False positive
0
Unauthorized
View authority model →

IMS Health Overview

DCMA-aligned checks · Snapshot S-39
Logic IntegrityMedium
92%
4 findingsImproving
Critical PathHigh
84%
3 findingsAttention Required
ConstraintsLow
95%
1 findingsStable
MilestonesHigh
78%
3 findings3 moved > 5 days
Status CurrencyMedium
96%
2 findings7 stale activities
DependenciesHigh
81%
8 findings8 external unresolved
Resource LoadingLow
89%
1 findingsStable
Baseline VarianceMedium
86%
5 findingsWatch

Priority Findings Awaiting Review

All findings →
  • Critical
    Critical Path Exposure
    Activity 4.3.2 has moved within three days of the critical path.
  • High
    Milestone Movement
    Milestone M-017 moved from October 20 to October 28.
  • High
    Missing Successor
    Activity 3.2.17 has no successor relationship.
  • High
    External Dependency
    Activity 5.1.4 depends on external delivery confirmation that remains unresolved.
  • High
    Interface Agreement Signature Pending
    M-010 moved +6 days pending PEO C4I signature.

Milestone Watchlist

Milestones →
  • Critical Design Review Complete10-09Watch
  • Software Code Freeze10-14Watch
  • External Interface Agreements Executed10-13At Risk
  • Integration Readiness10-23Watch
  • Site Readiness Certified11-06Decision Required
  • Initial Operational Capability01-14Watch
  • Operational Assessment Complete10-28Decision Required