Authoritative IMS · Microsoft Project · Snapshot S-39
Integrated Master Schedule
Read-only controlled copy. Select any activity for Cera activity intelligence.
Official Project Record · Read-only to Cera
76 of 76 activities
| Dur | Pred | Succ | Status | Org | BL Finish | Cur Finish | Crit | MarAprMayJunJulAugSepOctNovDecJanFeb | |||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2.3.1 | PDR Package Preparation | Jul 20 | Aug 4 | 15d | 2.2.2 | 2.3.2 | 0d | Complete | 100% | Navique Systems Engineering | Aug 4 | Aug 4 | 0d | ||
| 2.3.2 | Preliminary Design Review | Aug 4 | Aug 7 | 3d | 2.3.1 | 2.3.3, 4.1.1, M-007 | 0d | Complete | 100% | Navique Systems Engineering | Aug 7 | Aug 7 | 0d | ||
| 2.3.3 | CDR Package Preparation | Aug 24 | Sep 15 | 22d | 2.3.2, 2.2.4 | 2.3.4 | 0d | Complete | 100% | Navique Systems Engineering | Sep 15 | Sep 15 | 0d | ||
| 2.3.4 | Critical Design Review | Sep 23 | Oct 9 | 16d | 2.3.3 | M-008 | 6d | In Progress | 60% | Navique Systems Engineering | Oct 5 | Oct 9 | +4d | ||
| M-007 | Preliminary Design Review Complete | Aug 7 | Aug 7 | 0d | 2.3.2 | — | 0d | Complete | 100% | Chief Engineer | Aug 7 | Aug 7 | 0d | ||
| M-008 | Critical Design Review Complete | Oct 9 | Oct 9 | 0d | 2.3.4 | — | 6d | Not Started | 0% | Chief Engineer | Oct 5 | Oct 9 | +4d | ||
| 2.4.5 | ICD Government ReviewEXT | Aug 9 | Aug 29 | 20d | 2.2.4 | 2.4.6, 2.4.7 | 0d | Complete | 100% | NIWC Pacific PMO | Aug 29 | Aug 29 | 0d | ||
| 2.4.6 | External Interface Agreement ExecutionEXT | Aug 29 | Oct 19 | 51d | 2.4.5 | 3.2.4, M-010 | 7d | In Progress | 65% | PEO C4I | Oct 13 | Oct 19 | +6d | ||
| 2.4.7 | Interface Verification Plan | Sep 18 | Oct 18 | 30d | 2.4.5 | 2.4.8 | 5d | In Progress | 43% | Navique Systems Engineering | Oct 18 | Oct 18 | 0d | ◐ | |
| 2.4.8 | Interface Verification Procedures | Oct 18 | Nov 7 | 20d | 2.4.7 | — | 9d | Not Started | 0% | Navique Systems Engineering | Nov 7 | Nov 7 | 0d | ||
| M-010 | External Interface Agreements Executed | Oct 13 | Oct 13 | 0d | 2.4.6 | — | 7d | Not Started | 0% | Interface Manager | Oct 7 | Oct 13 | +6d | ||
| 3.1.1 | Sprint Planning & Backlog Refinement | Jun 30 | Jul 10 | 10d | — | 3.1.2, 3.1.3, 3.1.4 | 0d | Complete | 100% | Navique Software Engineering | Jul 10 | Jul 10 | 0d | ||
| 3.1.2 | Core Services Development | Jul 10 | Sep 8 | 60d | 3.1.1 | 3.1.5, 3.2.2 | 0d | Complete | 100% | Navique Software Engineering | Sep 8 | Sep 8 | 0d | ||
| 3.1.3 | Data Integration Layer | Jul 20 | Sep 13 | 55d | 3.1.1 | 3.1.6 | 0d | Complete | 100% | Navique Software Engineering | Sep 13 | Sep 13 | 0d | ||
| 3.1.4 | Operator Interface Development | Jul 30 | Sep 26 | 58d | 3.1.1 | 3.1.6 | 0d | Complete | 100% | Navique Software Engineering | Sep 26 | Sep 26 | 0d | ||
| 3.1.5 | Security Hardening & STIG Compliance | Sep 8 | Oct 11 | 33d | 3.1.2 | 3.1.6 | 8d | In Progress | 70% | Navique Software Engineering | Oct 8 | Oct 11 | +3d | ||
| 3.1.6 | Software Code Freeze | Oct 10 | Oct 14 | 4d | 3.1.5, 3.1.3, 3.1.4 | 4.1.3, M-009 | 8d | Not Started | 0% | Navique Software Engineering | Oct 11 | Oct 14 | +3d | ||
| M-009 | Software Code Freeze | Oct 14 | Oct 14 | 0d | 3.1.6 | — | 8d | Not Started | 0% | Software Lead | Oct 11 | Oct 14 | +3d | ||
| 3.2.1 | Integration Environment SetupEXT | Aug 14 | Sep 3 | 20d | — | 3.2.2, 3.2.3, 3.2.4, 3.2.17 | 0d | Complete | 100% | Navique Integration | Sep 3 | Sep 3 | 0d | ||
| 3.2.2 | Subsystem A Integration | Sep 3 | Sep 25 | 22d | 3.2.1, 3.1.2 | 3.2.18, 4.3.1 | 0d | Complete | 100% | Navique Integration | Sep 25 | Sep 25 | 0d | ||
| 3.2.3 | Subsystem B Integration | Sep 10 | Oct 6 | 26d | 3.2.1 | 3.2.18 | 10d | In Progress | 81% | Navique Integration | Oct 4 | Oct 6 | +2d | ||
| 3.2.4 | GFE Interface IntegrationEXT | Sep 18 | Oct 21 | 33d | 3.2.1, 2.4.6 | 3.2.5, 3.2.18 | 4d | In Progress | 39% | NIWC Pacific GFE | Oct 16 | Oct 21 | +5d | ◐ | |
| 3.2.5 | End-to-End Thread Integration | Oct 13 | Nov 2 | 20d | 3.2.4 | — | 4d | Not Started | 0% | Navique Integration | Nov 2 | Nov 2 | 0d | ◐ | |
| 3.2.17 | Integration Lab Decommission Plan | Oct 3 | Oct 11 | 8d | 3.2.1 | — | 39d | Not Started | 0% | Navique Integration | Oct 11 | Oct 11 | 0d | ||
| 3.2.18 | Integration Readiness Checkpoint | Oct 16 | Oct 18 | 2d | 3.2.2, 3.2.3, 3.2.4 | 4.2.1, M-011 | 0d | Not Started | 0% | Navique Integration | Oct 18 | Oct 18 | 0d | ● | |
| M-011 | Integration Readiness | Oct 23 | Oct 23 | 0d | 3.2.18 | — | 0d | Not Started | 0% | Integration Lead | Oct 18 | Oct 23 | +5d | ● | |
| 4.1.1 | TEMP Update | Jul 30 | Aug 19 | 20d | 2.3.2 | 4.1.2 | 0d | Complete | 100% | NIWC Pacific T&E | Aug 19 | Aug 19 | 0d | ||
| 4.1.2 | Test Procedures Development | Aug 19 | Sep 23 | 35d | 4.1.1 | 4.1.3 | 0d | Complete | 100% | NIWC Pacific T&E | Sep 23 | Sep 23 | 0d | ||
| 4.1.3 | Test Readiness Review Preparation | Oct 13 | Oct 23 | 10d | 4.1.2, 3.1.6 | 4.2.1, M-012 | 6d | Not Started | 0% | NIWC Pacific T&E | Oct 23 | Oct 23 | 0d | ||
| M-012 | Test Readiness Review | Oct 23 | Oct 23 | 0d | 4.1.3 | 4.2.1 | 6d | Not Started | 0% | T&E Lead (NIWC Pacific) | Oct 23 | Oct 23 | 0d | ||
| 4.2.1 | System Test ExecutionEXT | Nov 2 | Dec 2 | 30d | 4.1.3, 3.2.18, M-012 | 4.2.2 | 0d | Not Started | 0% | NIWC Pacific T&E | Dec 2 | Dec 2 | 0d | ● | |
| 4.2.2 | Regression Testing | Dec 2 | Dec 17 | 15d | 4.2.1 | 4.2.3, 5.2.2 | 0d | Not Started | 0% | NIWC Pacific T&E | Dec 17 | Dec 17 | 0d | ● | |
| 4.2.3 | System Test Report | Dec 17 | Dec 27 | 10d | 4.2.2 | M-014 | 0d | Not Started | 0% | NIWC Pacific T&E | Dec 27 | Dec 27 | 0d | ● | |
| M-014 | System Test Complete | Dec 27 | Dec 27 | 0d | 4.2.3 | — | 0d | Not Started | 0% | T&E Lead (NIWC Pacific) | Dec 27 | Dec 27 | 0d | ● | |
| 4.3.1 | Integration Verification | Sep 8 | Sep 30 | 22d | 3.2.2 | 4.3.2 | 0d | Complete | 100% | NIWC Pacific T&E | Sep 24 | Sep 30 | +6d | ||
| 4.3.2 | Operational AssessmentEXT | Oct 12 | Oct 28 | 16d | 4.3.1 | 4.3.3, M-017 | 3d | In Progress | 45% | NIWC Pacific T&E | Oct 20 | Oct 28 | +8d | ◐ | |
| 4.3.3 | Operational Assessment Report | Oct 28 | Nov 9 | 12d | 4.3.2 | 4.3.4 | 3d | Not Started | 0% | NIWC Pacific T&E | Nov 9 | Nov 9 | 0d | ◐ | |
| 4.3.4 | Government OA Acceptance | Nov 12 | Nov 17 | 5d | M-017, 4.3.3 | — | 3d | Not Started | 0% | NIWC Pacific PMO | Nov 17 | Nov 17 | 0d | ◐ | |
| M-017 | Operational Assessment Complete | Oct 28 | Oct 28 | 0d | 4.3.2 | 4.3.4 | 3d | Not Started | 0% | T&E Lead (NIWC Pacific) | Oct 20 | Oct 28 | +8d | ◐ | |
| 5.1.1 | Site Survey & Requirements | Aug 29 | Sep 13 | 15d | — | 5.1.2, 5.1.4 | 0d | Complete | 100% | NIWC Pacific Fleet Support | Sep 13 | Sep 13 | 0d | ||
| 5.1.2 | Facility Power & HVAC ModificationsEXT | Sep 16 | Oct 30 | 44d | 5.1.1 | 5.1.5 | 9d | In Progress | 34% | NAVFAC Southwest | Oct 26 | Oct 30 | +4d | ||
| 5.1.3 | Network Accreditation (ATO)EXT | Sep 23 | Nov 12 | 50d | 2.2.3 | 5.2.3 | 6d | In Progress | 16% | NIWC Pacific Cyber | Nov 12 | Nov 12 | 0d | ||
| 5.1.4 | Hardware Delivery ConfirmationEXT | Oct 5 | Oct 22 | 17d | 5.1.1 | 5.1.5 | 2d | Not Started | 0% | DLA / OEM Vendor | Oct 15 | Oct 22 | +7d | ◐ | |
| 5.1.5 | Equipment Rack Installation Prep | Oct 18 | Nov 6 | 19d | 5.1.4, 5.1.2 | 5.2.1, M-013 | 2d | Not Started | 0% | NIWC Pacific Fleet Support | Oct 30 | Nov 6 | +7d | ◐ | |
| M-013 | Site Readiness Certified | Nov 6 | Nov 6 | 0d | 5.1.5 | 5.2.1 | 2d | Not Started | 0% | Site Lead (NIWC Pacific) | Oct 30 | Nov 6 | +7d | ◐ | |
| 5.2.1 | Hardware Installation | Nov 17 | Dec 2 | 15d | 5.1.5, M-013 | 5.2.2 | 16d | Not Started | 0% | NIWC Pacific Fleet Support | Dec 2 | Dec 2 | 0d | ||
| 5.2.2 | Software Installation & Configuration | Dec 2 | Dec 12 | 10d | 5.2.1, 4.2.2 | 5.2.3 | 0d | Not Started | 0% | NIWC Pacific Fleet Support | Dec 12 | Dec 12 | 0d | ● | |
| 5.2.3 | Site Acceptance Test | Dec 17 | Dec 29 | 12d | 5.2.2, 5.1.3 | 5.3.1, 5.3.2, M-015 | 0d | Not Started | 0% | NIWC Pacific Fleet Support | Dec 29 | Dec 29 | 0d | ● | |
| M-015 | Site Acceptance Complete | Dec 29 | Dec 29 | 0d | 5.2.3 | — | 0d | Not Started | 0% | Site Lead (NIWC Pacific) | Dec 29 | Dec 29 | 0d | ● | |
| 5.3.1 | Operator TrainingEXT | Dec 29 | Jan 13 | 15d | 5.2.3 | 5.3.3, M-016 | 0d | Not Started | 0% | NIWC Pacific Fleet Support | Jan 13 | Jan 13 | 0d | ● | |
| 5.3.2 | O&M Documentation Handover | Dec 29 | Jan 12 | 14d | 5.2.3 | M-016 | 1d | Not Started | 0% | NIWC Pacific Fleet Support | Jan 12 | Jan 12 | 0d | ◐ | |
| 5.3.3 | Sustainment Transition Plan | Jan 13 | Jan 28 | 15d | 5.3.1 | 5.3.4 | 19d | Not Started | 0% | NIWC Pacific Fleet Support | Jan 28 | Jan 28 | 0d | ||
| 5.3.4 | Transition to In-Service Support | Jan 28 | Feb 7 | 10d | 5.3.3 | — | 20d | Not Started | 0% | NIWC Pacific Fleet Support | Feb 7 | Feb 7 | 0d | ||
| M-016 | Initial Operational Capability | Jan 14 | Jan 14 | 0d | 5.3.1, 5.3.2 | — | 0d | Not Started | 0% | NIWC Pacific PM | Jan 14 | Jan 14 | 0d | ● | |
Critical Near critical Normal Baseline Status date Oct 1 Cera finding