OSA Tools Project Management · NIWC Pacific
IMS Status Date Oct 1, 2026 · Snapshot S-39 · Navique Corporation
Change Detection

Schedule Changes

Comparing Previous IMS Snapshot S-38 (Sep 24, 2026) versus Current IMS S-39 (Oct 1, 2026).

Total Changes
37
High Impact
8
Decision Required
2
No Action
22
ActivityChangePreviousCurrentVarianceCera Assessment
Operational Assessment
Finish Date
Finish Changes
Oct 20Oct 28+8dHighReview
Operational Assessment Complete
Milestone
Milestone Changes
Oct 20Oct 28+8dHighDecision Required
Integration Verification
Actual Finish
Finish Changes
Sep 24Sep 30+6dHighReview
External Interface Agreements Executed
Milestone
Milestone Changes
Oct 15Oct 19+4dHighReview
Site Readiness Certified
Milestone
Milestone Changes
Oct 20Oct 27+7dHighDecision Required
Hardware Delivery Confirmation
Finish Date
Finish Changes
Oct 15Oct 22+7dHighReview
Operational Assessment
Near-Critical Entry
Critical Path Changes
Float 11dFloat 3d-8dHighReview
Integration Lab Decommission Plan
Successor Removed
Logic Changes
FS → 3.2.18No successor—HighReview
Interface Verification Plan
Total Float
Float Changes
14d5d-9dMediumMonitor
GFE Interface Integration
Finish Date
Finish Changes
Oct 17Oct 21+4dMediumReview
Interface Verification Plan
Near-Critical Entry
Critical Path Changes
Float 14dFloat 5d-9dMediumMonitor
Critical Design Review
Duration
Duration Changes
12d16d+4dMediumMonitor
3.2.9 Legacy Data Migration Rehearsal (deleted)
Activity Deleted
Deleted Activities
Legacy Data Migration Rehearsal——MediumReview
Facility Power & HVAC Modifications
Constraint Added
Constraint Changes
NoneSNET Sep 17—MediumMonitor
Subsystem B Integration
Resource Loading
Resource Changes
4 engineers3 engineers-1MediumMonitor
Cera Pilot Governance Framework
Activity Added
Added Activities
—Cera Pilot Governance Framework—LowNo Action
Monthly Program Management Reviews
Start Date
Start Changes
Apr 10Apr 11+1dLowNo Action
Integration Readiness Checkpoint
Finish Date
Finish Changes
Oct 20Oct 18-2dLowNo Action
Network Accreditation (ATO)
Duration
Duration Changes
49d50d+1dLowNo Action
Sustainment Transition Plan
Total Float
Float Changes
21d19d-2dLowNo Action
Software Code Freeze
Start Date
Start Changes
Oct 9Oct 10+1dLowNo Action
Operational Assessment Report
Finish Date
Finish Changes
Nov 11Nov 9-2dLowNo Action
Operator Training
Duration
Duration Changes
14d15d+1dLowNo Action
Interface Verification Procedures
Total Float
Float Changes
11d9d-2dLowNo Action
Regression Testing
Start Date
Start Changes
Dec 1Dec 2+1dLowNo Action
Software Installation & Configuration
Finish Date
Finish Changes
Dec 14Dec 12-2dLowNo Action
Quarterly Government Program Review
Duration
Duration Changes
2d3d+1dLowNo Action
Test Readiness Review Preparation
Total Float
Float Changes
8d6d-2dLowNo Action
Equipment Rack Installation Prep
Start Date
Start Changes
Oct 17Oct 18+1dLowNo Action
Transition to In-Service Support
Finish Date
Finish Changes
Feb 9Feb 7-2dLowNo Action
End-to-End Thread Integration
Duration
Duration Changes
19d20d+1dLowNo Action
Government OA Acceptance
Total Float
Float Changes
5d3d-2dLowNo Action
O&M Documentation Handover
Start Date
Start Changes
Dec 28Dec 29+1dLowNo Action
Security Hardening & STIG Compliance
Finish Date
Finish Changes
Oct 13Oct 11-2dLowNo Action
System Test Report
Duration
Duration Changes
9d10d+1dLowNo Action
Site Acceptance Test
Total Float
Float Changes
2d0d-2dLowNo Action
External Interface Agreement Execution
Start Date
Start Changes
Aug 28Aug 29+1dLowNo Action