Dependency Intelligence
Dependency Map
Activities and milestones as a logic network. Select a node to trace cascading impacts.
"Eight unresolved external dependencies affect 14 downstream activities. Two currently influence near-critical work (3.2.4, 4.3.2)."
Selected node
Integration Verification
Finish
Sep 30
Float
0d
Variance
6d
Org
NIWC Pacific T&E
Cascading impact: 4 downstream items
External dependencies
- EXT-01 · 2.4.6UnresolvedPEO C4I signature on External Interface AgreementPEO C4I · need Oct 9 · 3 downstream
- EXT-02 · 3.2.4UnresolvedGFE interface simulator deliveryNIWC Pacific GFE · need Oct 5 · 2 downstream · near-critical
- EXT-03 · 5.1.2UnresolvedNAVFAC facility power upgrade completionNAVFAC Southwest · need Oct 26 · 1 downstream
- EXT-04 · 5.1.3UnresolvedAuthorizing Official ATO decisionNIWC Pacific Cyber · need Nov 20 · 2 downstream
- EXT-05 · 5.1.4UnresolvedVendor ship-date confirmation for server hardwareDLA / OEM Vendor · need Oct 12 · 2 downstream
- EXT-06 · 4.2.1UnresolvedFleet test asset availabilityCOMPACFLT · need Nov 2 · 2 downstream
- EXT-07 · 5.3.1UnresolvedFleet operator availability for trainingCOMPACFLT · need Jan 4 · 1 downstream
- EXT-08 · 4.3.2UnresolvedFleet range-time allocation for Operational AssessmentCOMPACFLT · need Oct 12 · 1 downstream · near-critical
- EXT-09 · 2.4.5ResolvedGovernment ICD comment adjudicationNIWC Pacific PMO · need Aug 28 · 2 downstream
- EXT-10 · 3.2.1ResolvedGFE integration lab hardwareNIWC Pacific GFE · need Aug 15 · 4 downstream
CriticalExternalUnresolvedCascade