OSA Tools Project Management · NIWC Pacific
IMS Status Date Oct 1, 2026 · Snapshot S-39 · Navique Corporation
Dependency Intelligence

Dependency Map

Activities and milestones as a logic network. Select a node to trace cascading impacts.

AI Observation

"Eight unresolved external dependencies affect 14 downstream activities. Two currently influence near-critical work (3.2.4, 4.3.2)."

1.1.4Monthly Program Managem…1.2.3Cera Pilot Governance F…1.2.4Quarterly Government Pr…2.3.4 +4dCritical Design Review2.4.6 +6dExternal Interface Agre…2.4.7Interface Verification …2.4.8Interface Verification …3.1.5 +3dSecurity Hardening & ST…3.1.6 +3dSoftware Code Freeze3.2.3 +2dSubsystem B Integration3.2.4 +5dGFE Interface Integrati…3.2.5End-to-End Thread Integ…3.2.17Integration Lab Decommi…3.2.18Integration Readiness C…4.1.3Test Readiness Review P…4.2.1System Test Execution4.2.2Regression Testing4.2.3System Test Report4.3.1 +6dIntegration Verification4.3.2 +8dOperational Assessment4.3.3Operational Assessment …4.3.4Government OA Acceptance5.1.2 +4dFacility Power & HVAC M…5.1.3Network Accreditation (…5.1.4 +7dHardware Delivery Confi…5.1.5 +7dEquipment Rack Installa…5.2.1Hardware Installation5.2.2Software Installation &…5.2.3Site Acceptance Test5.3.1Operator Training5.3.2O&M Documentation Hando…5.3.3Sustainment Transition …5.3.4Transition to In-Servic…M-008 +4dCritical Design Review …M-009 +3dSoftware Code FreezeM-010 +6dExternal Interface Agre…M-011 +5dIntegration ReadinessM-012Test Readiness ReviewM-013 +7dSite Readiness CertifiedM-014System Test CompleteM-015Site Acceptance CompleteM-016Initial Operational Cap…M-017 +8dOperational Assessment …

Selected node

Integration Verification
Finish
Sep 30
Float
0d
Variance
6d
Org
NIWC Pacific T&E
Cascading impact: 4 downstream items

External dependencies

  • EXT-01 · 2.4.6Unresolved
    PEO C4I signature on External Interface Agreement
    PEO C4I · need Oct 9 · 3 downstream
  • EXT-02 · 3.2.4Unresolved
    GFE interface simulator delivery
    NIWC Pacific GFE · need Oct 5 · 2 downstream · near-critical
  • EXT-03 · 5.1.2Unresolved
    NAVFAC facility power upgrade completion
    NAVFAC Southwest · need Oct 26 · 1 downstream
  • EXT-04 · 5.1.3Unresolved
    Authorizing Official ATO decision
    NIWC Pacific Cyber · need Nov 20 · 2 downstream
  • EXT-05 · 5.1.4Unresolved
    Vendor ship-date confirmation for server hardware
    DLA / OEM Vendor · need Oct 12 · 2 downstream
  • EXT-06 · 4.2.1Unresolved
    Fleet test asset availability
    COMPACFLT · need Nov 2 · 2 downstream
  • EXT-07 · 5.3.1Unresolved
    Fleet operator availability for training
    COMPACFLT · need Jan 4 · 1 downstream
  • EXT-08 · 4.3.2Unresolved
    Fleet range-time allocation for Operational Assessment
    COMPACFLT · need Oct 12 · 1 downstream · near-critical
  • EXT-09 · 2.4.5Resolved
    Government ICD comment adjudication
    NIWC Pacific PMO · need Aug 28 · 2 downstream
  • EXT-10 · 3.2.1Resolved
    GFE integration lab hardware
    NIWC Pacific GFE · need Aug 15 · 4 downstream
CriticalExternalUnresolvedCascade