Related IMS Activity
Potential Schedule Impact
11 working daysAlternatives
- Approve revised sequence (Subsystem B before GFE)
- Retain current sequence and accept M-011 risk
- Defer GFE integration to post-TRR
Evidence
- Current IMS
- Integration Lead proposal
- R-028
- R-021
Decision Support
AI RecommendationRevised sequence recovers an estimated 6 of 11 days of exposure by decoupling Subsystem B from GFE simulator delivery. Trade-off: re-test of Subsystem A interfaces (~3 days).
Cera presents trade-offs only. The decision owner (Project Manager) holds authority for this decision.