01Executive Schedule Assessment

IMS health is 87/100 (Stable). 37 changes were detected since the prior status. Three milestones moved more than five working days (M-017, M-013, M-010) and two activities entered the near-critical band (4.3.2, 2.4.7). 8 external dependencies remain unresolved and 8 decisions are pending.

02Changes Since Previous Status

  • Finish Date: Oct 20 → Oct 28 (+8d)
  • Milestone: Oct 20 → Oct 28 (+8d)
  • Actual Finish: Sep 24 → Sep 30 (+6d)
  • Milestone: Oct 15 → Oct 19 (+4d)
  • Milestone: Oct 20 → Oct 27 (+7d)
  • Finish Date: Oct 15 → Oct 22 (+7d)
  • Near-Critical Entry: Float 11d → Float 3d (-8d)
  • Successor Removed: FS → 3.2.18 → No successor (—)
All 37 changes →

03Critical Path

Critical path runs through 3.2.18 Integration Readiness → 4.2.x System Test → 5.2.x Installation → M-016 IOC with zero float. 4.3.2 Operational Assessment is 3 days from the critical path; 3.2.4 GFE Interface Integration has 4 days.

04Milestones

Critical Design Review CompleteOct 5 → Oct 9+4d vs BLWatch
Software Code FreezeOct 11 → Oct 14+3d vs BLWatch
External Interface Agreements ExecutedOct 9 → Oct 13+6d vs BLAt Risk
Integration ReadinessOct 19 → Oct 23+5d vs BLWatch
Site Readiness CertifiedOct 30 → Nov 6+7d vs BLDecision Required
Operational Assessment CompleteOct 20 → Oct 28+8d vs BLDecision Required

05External Dependencies

  • PEO C4I signature on External Interface Agreement — PEO C4I, need Oct 9
  • GFE interface simulator delivery — NIWC Pacific GFE, need Oct 5
  • NAVFAC facility power upgrade completion — NAVFAC Southwest, need Oct 26
  • Authorizing Official ATO decision — NIWC Pacific Cyber, need Nov 20
  • Vendor ship-date confirmation for server hardware — DLA / OEM Vendor, need Oct 12
  • Fleet test asset availability — COMPACFLT, need Nov 2
  • Fleet operator availability for training — COMPACFLT, need Jan 4
  • Fleet range-time allocation for Operational Assessment — COMPACFLT, need Oct 12

06Schedule Risks

Elevated: R-031 range-time availability (M-017), R-028 interface agreement signature (M-010), R-033 hardware supply chain (M-013). Cera observations not yet in the official register: 3.

07Decisions Required

  • DEC-024 Approve revised integration sequence? — Project Manager, by Oct 9
  • DEC-025 Pursue recovery or rebaseline M-017 Operational Assessment Complete? — NIWC Pacific PM, by Oct 8
  • DEC-026 Request expedited hardware shipment? — Project Manager, by Oct 6
  • DEC-027 Approve CDR closure criteria with open RFAs? — NIWC Pacific Chief Engineer, by Oct 5
  • DEC-028 Authorize additional integration engineer for Subsystem B? — Project Manager, by Oct 10
  • DEC-029 Accept SNET constraint on facility modifications? — Scheduler, by Oct 7

08Recommended Actions

  • Review recovery options before the next status cycle. (AI Recommendation · pending review)
  • Prepare a variance narrative and decide on recovery vs. rebaseline. (AI Recommendation · pending review)
  • Scheduler to restore or justify the removed successor relationship. (AI Recommendation · pending review)
  • Request expedited confirmation through DLA and record decision DEC-026. (AI Recommendation · pending review)
  • Escalate through NIWC Pacific PM. (AI Recommendation · pending review)
  • Scheduler and T&E Lead to evaluate SS+5 relationship. (AI Recommendation · pending review)

09Items Cera Is Monitoring

  • 3.2.4 GFE Interface Integration float is 4 days.
  • 4.2.x chain remains on critical path with zero float.
  • 5.1.3 Network Accreditation float 6 days; AO decision pending.
  • 5.3.1 depends on fleet operator availability (Jan 2027).

10Actions Completed Since Previous Brief

  • CF-108 CDR Duration Growth accepted by Scheduler
  • 07:52 · Scheduler: Validated logic finding (CF-103)
  • 07:45 · Program Analyst: Requested Cera analysis (M-011)

11Evidence and Sources

Microsoft Project IMS (S-38, S-39), Approved Baseline BL-02, Excel status workbooks, SharePoint program library, Risk Register, Decision Register, external dependency register. Email was not accessed (not authorized).