Milestone Command View
Milestones
Baseline versus forecast for all tracked program milestones. Select a milestone for Cera's assessment.
Aug 2026Timeline · baseline (outline) → forecast (filled)Jan 2027
Status Oct 1
| Milestone | Baseline | Forecast | Variance | Confidence | Status | Owner | Dependencies | Risk Exposure |
|---|---|---|---|---|---|---|---|---|
| M-003 Contract Kickoff Complete(complete) | Mar 7 | Mar 7 | 0d | 100% | On Track | Navique PM | Low | |
| M-004 IMS Baseline Approved(complete) | Mar 27 | Mar 27 | 0d | 100% | On Track | Navique PM | Low | |
| M-005 Integrated Baseline Review(complete) | Apr 11 | Apr 11 | 0d | 100% | On Track | NIWC Pacific PM | Low | |
| M-006 System Requirements Review(complete) | May 26 | May 26 | 0d | 100% | On Track | Chief Engineer | Low | |
| M-007 Preliminary Design Review Complete(complete) | Aug 7 | Aug 7 | 0d | 100% | On Track | Chief Engineer | Low | |
| M-008 Critical Design Review Complete | Oct 5 | Oct 9 | +4d | 81% | Watch | Chief Engineer | Moderate | |
| M-009 Software Code Freeze | Oct 11 | Oct 14 | +3d | 84% | Watch | Software Lead | Moderate | |
| M-010 External Interface Agreements Executed | Oct 7 | Oct 13 | +6d | 62% | At Risk | Interface Manager | High | |
| M-011 Integration Readiness | Oct 18 | Oct 23 | +5d | 74% | Watch | Integration Lead | Moderate | |
| M-012 Test Readiness Review | Oct 23 | Oct 23 | 0d | 88% | On Track | T&E Lead (NIWC Pacific) | Low | |
| M-013 Site Readiness Certified | Oct 30 | Nov 6 | +7d | 58% | Decision Required | Site Lead (NIWC Pacific) | High | |
| M-014 System Test Complete | Dec 27 | Dec 27 | 0d | 79% | On Track | T&E Lead (NIWC Pacific) | Moderate | |
| M-015 Site Acceptance Complete | Dec 29 | Dec 29 | 0d | 77% | On Track | Site Lead (NIWC Pacific) | Moderate | |
| M-016 Initial Operational Capability | Jan 14 | Jan 14 | 0d | 72% | Watch | NIWC Pacific PM | Moderate | |
| M-017 Operational Assessment Complete | Oct 20 | Oct 28 | +8d | 61% | Decision Required | T&E Lead (NIWC Pacific) | High |