OSA Tools Project Management · NIWC Pacific
IMS Status Date Oct 1, 2026 · Snapshot S-39 · Navique Corporation
Milestone Command View

Milestones

Baseline versus forecast for all tracked program milestones. Select a milestone for Cera's assessment.

Aug 2026Timeline · baseline (outline) → forecast (filled)Jan 2027
Status Oct 1
MilestoneBaselineForecastVarianceConfidenceStatusOwnerDependenciesRisk Exposure
M-003 Contract Kickoff Complete(complete)Mar 7Mar 70d100%On TrackNavique PMLow
M-004 IMS Baseline Approved(complete)Mar 27Mar 270d100%On TrackNavique PMLow
M-005 Integrated Baseline Review(complete)Apr 11Apr 110d100%On TrackNIWC Pacific PMLow
M-006 System Requirements Review(complete)May 26May 260d100%On TrackChief EngineerLow
M-007 Preliminary Design Review Complete(complete)Aug 7Aug 70d100%On TrackChief EngineerLow
M-008 Critical Design Review CompleteOct 5Oct 9+4d81%WatchChief EngineerModerate
M-009 Software Code FreezeOct 11Oct 14+3d84%WatchSoftware LeadModerate
M-010 External Interface Agreements ExecutedOct 7Oct 13+6d62%At RiskInterface ManagerHigh
M-011 Integration ReadinessOct 18Oct 23+5d74%WatchIntegration LeadModerate
M-012 Test Readiness ReviewOct 23Oct 230d88%On TrackT&E Lead (NIWC Pacific)Low
M-013 Site Readiness CertifiedOct 30Nov 6+7d58%Decision RequiredSite Lead (NIWC Pacific)High
M-014 System Test CompleteDec 27Dec 270d79%On TrackT&E Lead (NIWC Pacific)Moderate
M-015 Site Acceptance CompleteDec 29Dec 290d77%On TrackSite Lead (NIWC Pacific)Moderate
M-016 Initial Operational CapabilityJan 14Jan 140d72%WatchNIWC Pacific PMModerate
M-017 Operational Assessment CompleteOct 20Oct 28+8d61%Decision RequiredT&E Lead (NIWC Pacific)High