IMS Status Date Oct 1, 2026 · Snapshot S-39 · Navique Corporation
L1 · Recommend
Schedule Intelligence
Cera Intelligence
Continuous analysis of the Integrated Master Schedule and connected project information.
Observation
4.3.2 Operational Assessment finish moved from Oct 20 to Oct 28 (+8 working days). Total float dropped from 11 to 3 days.
Evidence
Current IMS (Oct 1 status)
Prior IMS Snapshot (Sep 24)
Activity 4.3.1
Baseline Schedule (BL-02)
Status Update dated October 1
Assessment
The movement is driven by predecessor 4.3.1 Integration Verification, which completed six days later than planned. Remaining float is insufficient to absorb a typical range-time delay.
Schedule Impact
M-017 Operational Assessment Complete moves +8d. A further slip of more than 3 days places 4.3.2 on the critical path and pushes 4.3.4 Government OA Acceptance.
Recommendation
Review recovery options before the next status cycle.
Confidence
High · 92%
Authority Boundary
Cera may recommend this action under Level 1 · Recommend but may not execute it. A human decision is required.
AcceptRejectNeeds RevisionMonitorEscalate
Add to Brief
HighAI ObservationCF-102
Milestone Movement
Milestone M-017 moved from October 20 to October 28.