OSA Tools Project Management · NIWC Pacific
IMS Status Date Oct 1, 2026 · Snapshot S-39 · Navique Corporation
Schedule Intelligence

Cera Intelligence

Continuous analysis of the Integrated Master Schedule and connected project information.

NIWC Pacific T&EDetected 10-01 06:42High · 92%L1 · Recommend
Pending Human Review
Observation
4.3.2 Operational Assessment finish moved from Oct 20 to Oct 28 (+8 working days). Total float dropped from 11 to 3 days.
Evidence
  • Current IMS (Oct 1 status)
  • Prior IMS Snapshot (Sep 24)
  • Activity 4.3.1
  • Baseline Schedule (BL-02)
  • Status Update dated October 1
Assessment
The movement is driven by predecessor 4.3.1 Integration Verification, which completed six days later than planned. Remaining float is insufficient to absorb a typical range-time delay.
Schedule Impact
M-017 Operational Assessment Complete moves +8d. A further slip of more than 3 days places 4.3.2 on the critical path and pushes 4.3.4 Government OA Acceptance.
Recommendation
Review recovery options before the next status cycle.
Confidence
High · 92%
Authority Boundary
Cera may recommend this action under Level 1 · Recommend but may not execute it. A human decision is required.
NIWC Pacific T&EDetected 10-01 06:43High · 96%L1 · Recommend
Pending Human Review
Navique IntegrationDetected 10-01 06:44High · 98%L1 · Recommend
Pending Human Review
NIWC Pacific Fleet SupportDetected 10-01 06:45High · 88%L1 · Recommend
Pending Human Review